Bruce A – SG High Pressure Fuel Delivery Skid System

Client: Kinetrics Inc.
Location: Tiverton, ON
Trades: IPiping, Electrical
Engineer: RCM Technologies

E.S. Fox Limited was a sub-contracted fabricator. Our scope included the supply of all material, labour, & equipment necessary to fabricate 5 SG fuel skids. The fuel skids were to be completed & ready for simple pipe flange tie-ins and single point power & instrumentation connection to existing facility installations. The QA Level is Z299.3. Fabrication of a two level structural steel frame, complete with grating & handrails, which houses all mechanical equipment, piping, electrical, & instrumentation installations.

The structure was built to CWB W59 code of construction. Fabrication & installation of all pipe/tube systems, complete with instrumentation.

Piping was performed to ASME B31.1 code of construction.

Installation of power & instrumentation wiring, complete with control panels & junctions.

Pressure testing, point-to-point, weld inspections, operational testing was performed during fabrication & prior to shipment.